FIELD TERMINAL UNIT (FTU)
SITE ACCEPTANCE TEST (SAT)
Doc No. SAT TP-FTU Rev. No. 2 Date 28 February 2024

CONTRACT TITLE :

PEMBEKALAN, PEMASANGAN DAN PENGUJIAN FIELD TERMINAL UNIT (FTU) UNTUK PROJEK DISTRIBUTION AUTOMATION (DA)



CONTRACT NO. : TNB2555/2023
CONTRACTOR : EMPIRE RHEA
DATE : 08-12-2025
SUBSTATION NAME : PE TAMAN PALONG
FUNCTIONAL LOCATION : ALOR/PCE/123
SUBZONE : ALOR SETAR
STATE : KEDAH
FTU BRAND : FRONTLINE ELECTRONICS
FTU SERIAL NUMBER :
EFI BRAND : EMG
EFI SERIAL NUMBER : EFI-1 : EXISTING
EFI-2 : EXISTING
EFI-3 : EXISTING
SITE COMPLETION CHECKLIST (SCC)
FIELD TERMINAL UNIT (FTU)
Doc No. SCC - FTU Rev. No. 2 Date 5 June 2020
A1. SCC FTU
CONTRACT NO : TNB2555/2023
FUNCTIONAL LOCATION : ALOR/PCE/123
SUBSTATION NAME : PE TAMAN PALONG
Check boxes as follows: (✓) OK     NI : Need Improvement (Pls. give comments at 'Remark' column)
No. Description OK NI REMARKS
1. Visual Checks on FTU Cabinet
i. FTU cabinet is properly mounted & aligned at the wall / designated area.
ii. QR code / label is available inside FTU Cabinet. Scan QR code and check contact (must be as per requirement in SOW).
[* If available for this contract]
iii. All wirings to the terminal blocks are terminated tightly and terminal blocks are in good condition.
iv. All cable glands/ adaptors at both FTU and EFIs are installed properly. The cables shall be properly glanded at the cable entry points using proper glanding and sealing (to ensure no space/gap between the cable entry points and the panel)
v. Nameplate/Sticker with information on Serial Number, Site Acceptance Test (SAT) date & Warranty period is available in cabinet.
vi. SAT date must be written clearly & in the correct text position on the Nameplate/Sticker.
2. Visual and Physical Checks on Cablings and Terminations
i. All non-armoured cables (including EFI CT cable) shall be installed in rigid high impact PVC conduits, neatly secured in position and adequately supported where necessary in an approved manner.
ii. The size of the PVC conduit shall be 25 mm in diameter and the colour of the conduit and fittings shall be orange. The conduits shall be fixed by means of saddles secured rigidly at intervals not exceeding 750 mm.
iii. Cable supports/brackets/elbows shall be installed at intervals not greater than 1500 mm for vertical runs and not greater than 1000 mm for horizontal runs. The brackets shall be derusted, finished in a primer and coated with standard orange enamel. The brackets/elbows shall not be painted.
iv. For armoured cables, cable supports, elbows, cleats, trays shall be used. All materials must be of galvanised type (of at least 1.2 mm in thickness).
v. Continuity tests shall be carried out for each core including spare cores.
Observations:
Checks conducted by:
Contractor's Signature & Stamp:
Verified by:
TNB's Representative Signature & Stamp:
Contractor Signature
Name: NAZRULL ZIQRAM Name:
Date: 08-12-2025 Date:
SITE COMPLETION CHECKLIST (SCC)
FIELD TERMINAL UNIT (FTU)
Doc No. SCC - FTU Rev. No. 2 Date 5 June 2020
A1. SCC FTU
CONTRACT NO : TNB2555/2023
FUNCTIONAL LOCATION : ALOR/PCE/123
SUBSTATION NAME : PE TAMAN PALONG
Check boxes as follows: (✓) OK     NI : Need Improvement (Pls. give comments at 'Remark' column)
No. Description OK NI REMARKS
3. Visual Checks on Installations
a. FTU equipment
i. All cablings and internal wirings for FTU modules and accessories are laid properly & neatly secured.
ii. All the I/O points (inclusive of spares and unused points) are wired internally, configured and ready for terminations from Field Devices, (complete with its terminal blocks/connectors/wires and all other necessary accessories).
iii. All cables for I/O signal, AC & Earth are laid & terminated according to FTU Technical Specification.
b. Earth Fault Indicators (EFIs)
i. Installed on a mounting board, at designated area with cable markings for each EFI.
ii. Not more than 2 nos. of EFIs on the mounting board.
iii. Printed stencils (black text on white, with laminated tape) are available for numbering on the mounting board.
iv. The EFI CT cables are laid and terminated from EFI to Switchgears (at the back or under the Switchgears).
4. Site Drawings & Tests
i. Hardcopy of Approved Drawings
- Documents are available & placed inside FTU cabinet.
[Note: Any changes to the drawings shall be updated in softcopy and passed to TNB as As-built drawings.]
ii. Hardcopy of Mastersheet & Wiring List (Working Copies)
- Any changes shall be updated/written in the Mastersheet & Wiring List & verified, signed and stamped by TNB supervisor / representative
- Documents are available & placed inside the FTU cabinet.
iii. Check & verify all necessary tests (including cable continuity tests for all cabling work) are performed as required & have passed.
Observations:
Checks conducted by:
Contractor's Signature & Stamp:
Verified by:
TNB's Representative Signature & Stamp:
Contractor Signature
Name: NAZRULL ZIQRAM Name:
Date: 08-12-2025 Date:
SITE COMPLETION CHECKLIST (SCC)
REMOTE TERMINAL UNIT
SITE ACCEPTANCE TEST (SAT)
Doc No. SCC - RTU (SAT) Rev. No. 1 Date 5 June 2020
CONTRACT NO. : TNB2555/2023
FUNCTIONAL LOCATION : ALOR/PCE/123
SUBSTATION NAME : PE TAMAN PALONG

Note: Please sketch the building layout and the location of:

a. RCB panel

b. Battery Charger

c. EFIs location

d. Switchgear Panel

e. RTU Panel

SITE DRAWING:
EFI
EFI
FEEDER
FEEDER
FEEDER
FTU
DB
DOOR
FIELD TERMINAL UNIT (FTU)
SITE ACCEPTANCE TEST (SAT)
Doc No. SAT TP-FTU Rev. No. 2 Date 28 February 2024

CONTRACT TITLE :

PEMBEKALAN, PEMASANGAN DAN PENGUJIAN FIELD TERMINAL UNIT (FTU) UNTUK PROJEK DISTRIBUTION AUTOMATION (DA)



CONTRACT NO. : TNB2555/2023
CONTRACTOR : EMPIRE RHEA
DATE : 08-12-2025
SUBSTATION NAME : PE TAMAN PALONG
FUNCTIONAL LOCATION : ALOR/PCE/123
SUBZONE : ALOR SETAR
STATE : KEDAH
FTU BRAND : FRONTLINE ELECTRONICS
FTU SERIAL NUMBER :
FIRMWARE VERSION: FTU – FW – 002 – 2017
FIELD TERMINAL UNIT (FTU)
SITE ACCEPTANCE TEST (SAT)
Doc No. SAT TP-FTU Rev. No. 2 Date 28 February 2024
TABLE OF CONTENT
A1. FTU PARAMETER SYSTEM CHECK
FTU Parameter Setting Check
Test Ref.
PC.1
A2. FTU SYSTEM’S FUNCTIONAL CHECK
FTU System’s Functional Check
Test Ref.
FC.1
A3. FTU MASTERSHEET RECORD
Mastersheet Record
Test Ref.
MS.1
FIELD TERMINAL UNIT (FTU)
SITE ACCEPTANCE TEST (SAT)
Doc No. SAT TP-FTU Rev. No. 2 Date 28 February 2024
A1. FTU PARAMETER SETTING CHECK
Test Ref: FTU Parameter Setting Check (Frontline Electronics)
PC.1
a) Site Acceptance Test List (FTU Parameter Setting Check)
No. Description Standard Setting YES NO REMARKS
1 Baudrate 9600
2 Source Address 1
3 Destination Address 5
4 Relay ON Time (ms) 3000
5 AC Fail Address 2
6 DC Low Address 3
7 Input 1 0
8 Input 2 1
9 Input 3 4
10 Input 4 5
11 FTU Model FE-TQ-FTU-022017
12 FTU FW Version FTU-FW-002-2017
Test Observations:
Test Result: PASS ☑ FAIL ☐
Checks conducted by:
Contractor's Signature & Stamp:
Verified by:
TNB's Representative Signature & Stamp:
Contractor Signature
Name: NAZRULL ZIQRAM Name:
Date: Date:
FIELD TERMINAL UNIT (FTU)
SITE ACCEPTANCE TEST (SAT)
Doc No. SAT TP-FTU Rev. No. 2 Date 28 February 2024
A1. FTU PARAMETER SETTING CHECK
Test Ref: FTU Parameter Setting Check (Frontline Electronics)
PC.1
Test Observations:
Test Result: PASS ☑ FAIL ☐
Checks conducted by:
Contractor's Signature & Stamp:
Verified by:
TNB's Representative Signature & Stamp:
Contractor Signature
Name: NAZRULL ZIQRAM Name:
Date: Date:
FIELD TERMINAL UNIT (FTU)
SITE ACCEPTANCE TEST (SAT)
Doc No. SAT TP-FTU Rev. No. 2 Date 28 February 2024
A2. FTU SYSTEM’S FUNCTIONAL CHECK
Test Ref: FTU System’s Functional Check
FC.1
a) Site Acceptance Test List (FTU Parameter Setting Check)
No. Description Procedures and Criteria YES/NO REMARKS
1 RID Configuration check All configurations and settings are set accordingly. YES
2 AC supply check at FTU Make sure MCB is ON and terminal shall has 240Vac. YES
3 AC supply check at EFI Check the voltage source at EFI to be 240Vac. YES
4 DC supply ON Check terminal MW +/- Bat. are: >12Vdc YES
5 I/O cable EFI 1 Press the test button at the EFI1. A signal shall be picked up at the Protocol Analyser. YES
6 I/O cable EFI 2 Press the test button at the EFI2. A signal shall be picked up at the Protocol Analyser. YES
7 I/O cable EFI 3 Press the test button at the EFI3. A signal shall be picked up at the Protocol Analyser.
8 I/O cable EFI 4 Press the test button at the EFI4. A signal shall be picked up at the Protocol Analyser.
9 LED light ok LED is light ON. Switch it OFF before closing the panel and leaving the station. YES
10 Test AC Fail Alarm Turn OFF the AC. Protocol Analyser shall pick-up the alarm. YES
11 Test DC Low Alarm Use a cable to short the MW’s AC OK terminal. Protocol Analyser shall pick-up the alarm. YES
12 Reset EFI 1 operate Use Protocol Analyser to simulate a reset signal. The EFI1 will start to flash (resetting). YES
13 Reset EFI 2 operate Use Protocol Analyser to simulate a reset signal. The EFI2 will start to flash (resetting). YES
14 Reset EFI 3 operate Use Protocol Analyser to simulate a reset signal. The EFI3 will start to flash (resetting).
15 Reset EFI 4 operate Use Protocol Analyser to simulate a reset signal. The EFI4 will start to flash (resetting).
Test Observations:
Test Result: PASS ☑ FAIL ☐
Checks conducted by:
Contractor's Signature & Stamp:
Verified by:
TNB's Representative Signature & Stamp:
Contractor Signature
Name: NAZRULL ZIQRAM Name:
Date: Date:
FIELD TERMINAL UNIT (FTU)
SITE ACCEPTANCE TEST (SAT)
Doc No. SAT TP-FTU Rev. No. 2 Date 28 February 2024
A3. FTU MASTERSHEET RECORD
Test Ref: Mastersheet Record
MS.1
PROTOCOL IEC 101:
No. Description Port Address IEC101 IOA IEC104 IOA Remarks
1 EFI 1 status
2 EFI 2 status
3 EFI 3 status
4 EFI 4 status
5 Spare
6 Spare
7 AC Fail
8 DC Low
9 EFI Reset
PROTOCOL DNP3:
No. Description Port Address DNP3 IOA IEC104 IOA Remarks
1 EFI 1 status 0 DONE
2 EFI 2 status 1 DONE
3 EFI 3 status 4 DONE
4 EFI 4 status 5 DONE
5 Spare - DONE
6 Spare - DONE
7 AC Fail 2 DONE
8 DC Low 3 DONE
9 EFI Reset 0 DONE
Test Observations:
Test Result: PASS ☑ FAIL ☐
Checks conducted by:
Contractor's Signature & Stamp:
Verified by:
TNB's Representative Signature & Stamp:
Contractor Signature
Name: NAZRULL ZIQRAM Name:
Date: Date:
SITE COMPLETION CHECKLIST (SCC)
REMOTE TERMINAL UNIT
(INSTALLATION)
Doc No. SCC - RTU (INS) Rev. No. 1 Date 5 June 2020
A2. PICTURES (BEFORE & AFTER DURING PRE-CABLING & INSTALLATION)
CONTRACT NO. : TNB2555/2023
FUNCTIONAL LOCATION : ALOR/PCE/123
SUBSTATION NAME : PE TAMAN PALONG
BEFORE INSTALLATION
OVERALL PICTURE OF SUBSTATION OUTER WALL (WITH SUBSTATION NAME) DESIGNATED SPACE/WALL FOR FTU BEFORE INSTALLATION EXISTING EFI(s) OR DESIGNATED SPACE/WALL FOR EFI INSTALLATION
EXISTING EFI(s) OR DESIGNATED SPACE/WALL FOR EFI INSTALLATION SECOND PICTURE (IF ANY)
AFTER INSTALLATION
OVERALL PICTURE OF SUBSTATION OUTER WALL (WITH SUBSTATION NAME) FTU AFTER INSTALLATION (WITH INSIDE PICTURE) FTU WARRANTY STICKER (COMPLETE WITH SAT DATE)
SITE COMPLETION CHECKLIST (SCC)
REMOTE TERMINAL UNIT
(INSTALLATION)
Doc No. SCC - RTU (INS) Rev. No. 1 Date 5 June 2020
A2. PICTURES (BEFORE & AFTER DURING PRE-CABLING & INSTALLATION)
CONTRACT NO. : TNB2555/2023
FUNCTIONAL LOCATION : ALOR/PCE/123
SUBSTATION NAME : PE TAMAN PALONG
AFTER INSTALLATION
OVERALL PICTURE OF MASTERSHEET INSIDE FTU PANEL EFI 1 (AFTER INSTALLATION) EFI 2 (AFTER INSTALLATION) (IF ANY)
EFI 3 (AFTER INSTALLATION) (IF ANY) EFI 4 (AFTER INSTALLATION) (IF ANY) SAMPLE EFI'S CT CABLE AT SWITCHGEAR (AFTER CLAMPED)
SAMPLE EFI'S CT CABLE AT SWITCHGEAR (AFTER CLAMPED) SECOND PICTURE (IF ANY) CABLES GLAND INSIDE FTU PANEL
Edit & Resubmit Form